Start Date | Start Time | End Date | End Time | Data Quality Metric |
---|---|---|---|---|
07/13/2009 | 0000 | 08/05/2009 | 0600 | Missing |
Subject: | NSA/SONDE/C1 - Wind data missing |
DataStreams: | nsasondewnpnC1.b1 |
Description: | After some power disruptions, the Power Supply board of the SPS220 ground station was damaged. The damage caused the supply to not have enough power to run the GPS board. Switching to the back up DigiCora II did not alleviate the problem as the fix for GPS failure to all Vaisala sonde products had not been installed. A different P/S was found and sent up to replace the failed one. |
Suggestions: | |
Measurements: | nsasondewnpnC1.b1: more
|