AWR/CPC/M1 - CPC Flooding
DataStreams:awraoscpcfM1.b1, awraoscpcfM1.a1
Description:
Following a routine flow rate check, the CPC showed signs of flooding with the orifice 
pressure dropping below 10 kPa.  The butanol fill bottle was removed from the system.  After 
two days of continuous running the system dried out and the orifice pressures were 
restored to nominal values.  The data from this period is suspect.
Suggestions: 
Measurements:awraoscpcfM1.a1:
  • concentration
more
awraoscpcfM1.b1:
  • concentration
more