DQR ID | Subject | Data Streams Affected |
---|---|---|
D040416.1 | TWP/GNDRAD/C3 - IRT bias | twpgndrad60sC3.b1 |
D050919.4 | TWP/GNDRAD/C3 - Tower inverted for instrument testing and replacement | twpgndrad60sC3.b1 |
D051206.5 | TWP/GNDRAD/C3 - IRT malfunction | twpgndrad60sC3.b1 |
D060111.1 | TWP/GNDRAD/C3 - IRT power | twpgndrad60sC3.b1 |
D060630.36 | TWP/GNDRAD/C3 - Reprocess: Longwave Calibration error | twpgndrad60sC3.b1 |
Start Date | Start Time | End Date | End Time |
---|---|---|---|
04/07/2004 | 0230 | 04/08/2004 | 1200 |
04/12/2004 | 0600 | 04/27/2004 | 1400 |
05/08/2004 | 0300 | 05/15/2004 | 2200 |
05/27/2004 | 1100 | 06/09/2004 | 0000 |
12/29/2004 | 1100 | 01/06/2005 | 2300 |
Subject: | TWP/GNDRAD/C3 - IRT bias |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The IRT behaved erratically, jumping frequently from reporting about 50 Wm^(-2) higher than the PIR for surface irradiance values to about 100Wm^(-2) lower than the PIR. Generally, the IRT measured lower surface temperatures than expected from the PIR. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
08/05/2005 | 0030 | 08/05/2005 | 0200 |
08/09/2005 | 0000 | 08/09/2005 | 0200 |
Subject: | TWP/GNDRAD/C3 - Tower inverted for instrument testing and replacement |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The tower at Darwin was brought down to test and replace the Gndrad PIR on 8/5/2005 and the PSP on 8/9/2005 |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
11/21/2005 | 1500 | 12/05/2005 | 0100 |
Subject: | TWP/GNDRAD/C3 - IRT malfunction |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The internal IRT power supply failed (probably due to a lightning strike on 11/14) and was drawing excessive current on the data logger's DC system. The problem was corrected by replacing the instrument with a spare. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
12/20/2005 | 2330 | 01/02/2006 | 2300 |
Subject: | TWP/GNDRAD/C3 - IRT power |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The IRT failed to report after a planned power outage to add lightning protection modules to the AC power wiring. The problem was corrected when a loose power connection to the logger was found, rectified, and power restored to the logger. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
05/20/2004 | 0100 | 12/21/2005 | 2137 |
Subject: | TWP/GNDRAD/C3 - Reprocess: Longwave Calibration error |
DataStreams: | twpgndrad60sC3.b1 |
Description: | Modified pyrgeometer calibration procedures were implemented beginning in December 2003. These modified procedures introduced a calibration bias in the longwave data. The previous procedures were re-implemented at all sites between December 2005 and February 2006 to restore proper calibrations. The data collected while the incorrect procedures were in place are being reprocessing to remove the calibration bias. Note, this also affected standard deviation, maximum and minimum data fields. |
Measurements: | twpgndrad60sC3.b1:
|