DQR ID | Subject | Data Streams Affected |
---|---|---|
D090211.6 | HFE/AOS/M1 - CCN missing | hfeaosccnM1.a1 |
D111122.2 | HFE/AOS/M1 - CPC and CCN data questionable | hfeaosccnM1.a1, hfenoaaaosM1.b1 |
Start Date | Start Time | End Date | End Time |
---|---|---|---|
07/08/2008 | 0320 | 07/25/2008 | 0429 |
Subject: | HFE/AOS/M1 - CCN missing |
DataStreams: | hfeaosccnM1.a1 |
Description: | A power regulator on the CCN circuit board failed. The mentor replaced it and it was up and working on 7/25/2008. |
Measurements: | hfeaosccnM1.a1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
07/25/2008 | 0000 | 12/28/2008 | 2300 |
Subject: | HFE/AOS/M1 - CPC and CCN data questionable |
DataStreams: | hfeaosccnM1.a1, hfenoaaaosM1.b1 |
Description: | The CPC slowly clogged and the signal declined until the instrument was cleaned at which point the signal would increase. The data is still a good relative measure of the daily changes in the CN concentration, but the absolute value may be too low. The mentor was unable to monitor the flow rate and operation in the CCN during operation. The relative changes in CCN with %ss are likely fine, but the absolute values may be too low or too high. Dust was prevalent at the site and likely contributed to the CCN signal such that large dust particles appeared as droplets. |
Measurements: | hfenoaaaosM1.b1:
hfeaosccnM1.a1:
|