DQRID : D091112.3
Start DateStart TimeEnd DateEnd Time
11/05/2009180911/25/20092000
more
Subject:
SGP/MFR10M/C1 - Bad connection
DataStreams:sgpmfr10mC1.b1, sgpmfr10mC1.a0
Description:
The instrument was pulled for quarterly calibration on 20091105.  When the instrument was 
reinstalled, the head cable was not making a good connection to the head.  Cleaning the 
connector and reinstalling resolved the issue.
Suggestions: 
Measurements:sgpmfr10mC1.b1:
  • 3 meter upwelling broadband hemispheric irradiance(up_hemisp_broadband)
  • 10 meter Narrowband Upwelling Hemispheric Irradiance, Filter 6(up_hemisp_narrowband_filter6)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 4(up_hemisp_narrowband_filter4)
  • 25 meter upwelling narrowband hemispheric irradiance, filter 5, offset corrected(up_hemisp_narrowband_filter5)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 2, offset corrected(up_hemisp_narrowband_filter2)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 3, offset corrected(up_hemisp_narrowband_filter3)
  • 10 meter upwelling narrowband hemispheric irradiance, filter 1(up_hemisp_narrowband_filter1)
more
sgpmfr10mC1.a0:
  • 10 meter upwelling narrowband hemispheric irradiance, filter 1(up_hemisp_narrowband_filter1)
  • 3 meter upwelling broadband hemispheric irradiance(up_hemisp_broadband)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 3, offset corrected(up_hemisp_narrowband_filter3)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 2, offset corrected(up_hemisp_narrowband_filter2)
  • 25 meter upwelling narrowband hemispheric irradiance, filter 5, offset corrected(up_hemisp_narrowband_filter5)
  • 3 meter upwelling narrowband hemispheric irradiance, filter 4(up_hemisp_narrowband_filter4)
  • 10 meter Narrowband Upwelling Hemispheric Irradiance, Filter 6(up_hemisp_narrowband_filter6)
more

Close this window