DQRID : D160624.2
Start DateStart TimeEnd DateEnd Time
04/24/2016183506/03/20161910
more
Subject:
NSA/GNDRAD/C1 - IRT wiring
DataStreams:nsagndrad60sC1.b1, nsagndrad60sC1.a1
Description:
When maintenance was performed on the GNDRAD tower, the IRT signal cable was re-connected 
incorrectly.
Suggestions: 
Do not use data
Measurements:nsagndrad60sC1.b1:
  • Surface infra-red temperature(sfc_ir_temp)
  • Surface Infra-Red Temperature, Standard Deviation(sfc_ir_temp_std)
  • Surface Infra-Red Temperature, Minima(sfc_ir_temp_min)
  • Surface Infra-Red Temperature, Maxima(sfc_ir_temp_max)
more
nsagndrad60sC1.a1:
  • Surface Infra-Red Temperature, Maxima(sfc_ir_temp_max)
  • Surface Infra-Red Temperature, Standard Deviation(sfc_ir_temp_std)
  • Surface Infra-Red Temperature, Minima(sfc_ir_temp_min)
  • Surface infra-red temperature(sfc_ir_temp)
more

Close this window