DQR ID | Subject | Data Streams Affected |
---|---|---|
D051114.2 | TWP/MWR/C3 - Instrument failure, Power outage | twpmwrC3.00, twpmwrlosC3.a1, twpmwrlosC3.b1, twpmwrtipC3.a1 |
D051114.3 | TWP/SKYRAD/C3 - tracker inoperative | twpskyradC3.00, twpskyrad20sC3.a0, twpskyrad60sC3.b1 |
D051206.5 | TWP/GNDRAD/C3 - IRT malfunction | twpgndrad60sC3.b1 |
D051214.1 | TWP/MWR/C3 - REPROCESS- Updated retrieval coefficients | twpmwrlosC3.b1, twpmwrtipC3.a1 |
D060110.3 | TWP/SKYRAD/C3 - IRT damaged | twpskyrad20sC3.a0, twpskyrad60sC3.b1 |
D060111.1 | TWP/GNDRAD/C3 - IRT power | twpgndrad60sC3.b1 |
D060426.8 | TWP/SMET/C3 - ORG data noisy due to degraded ground | twpsmet60sC3.b1 |
D060630.33 | TWP/SKYRAD/C3 - Reprocess: Longwave Calibration error | twpskyrad60sC3.b1 |
D060630.36 | TWP/GNDRAD/C3 - Reprocess: Longwave Calibration error | twpgndrad60sC3.b1 |
D060818.3 | TWP/SMET/C3 - Reprocess: Barometric Data Changed from hPa to kPa | twpsmet60sC3.b1 |
D061011.4 | TWP/SMET/C3 - Reprocess: Tipping bucket rain gauge added | twpsmet60sC3.b1 |
Start Date | Start Time | End Date | End Time |
---|---|---|---|
11/14/2005 | 0453 | 12/10/2005 | 0000 |
Subject: | TWP/MWR/C3 - Instrument failure, Power outage |
DataStreams: | twpmwrC3.00, twpmwrlosC3.a1, twpmwrlosC3.b1, twpmwrtipC3.a1 |
Description: | A lightning strike sent the MWR offline. The radiometer suffered extensive damage, was removed from the site and sent to the vendor for repair. A spare radiometer was sent to the TWP/C3 site and was installed on 12/07. However, some hardaware communication issues prevented data collection until 12/10. |
Measurements: | twpmwrlosC3.a1:
twpmwrlosC3.b1:
twpmwrtipC3.a1:
twpmwrC3.00:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
11/14/2005 | 0453 | 12/02/2005 | 0000 |
Subject: | TWP/SKYRAD/C3 - tracker inoperative |
DataStreams: | twpskyradC3.00, twpskyrad20sC3.a0, twpskyrad60sC3.b1 |
Description: | A lightning strike at Darwin removed the tracker from service. Instruments installed on the tracker were rendered either inoperative or were not shaded during this time period. The longwave hemispheric instruments PIR1 and PIR2 appear to have been unaffected. They are not suseptable to incorrect tracker operation. The downwelling hemispheric shortwave PSP instrument mounted on Skyrad will not be affected by incorrect tracker operation. |
Measurements: | twpskyradC3.00:
twpskyrad60sC3.b1:
twpskyrad20sC3.a0:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
11/21/2005 | 1500 | 12/05/2005 | 0100 |
Subject: | TWP/GNDRAD/C3 - IRT malfunction |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The internal IRT power supply failed (probably due to a lightning strike on 11/14) and was drawing excessive current on the data logger's DC system. The problem was corrected by replacing the instrument with a spare. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
02/27/2002 | 0000 | 12/12/2005 | 1600 |
Subject: | TWP/MWR/C3 - REPROCESS- Updated retrieval coefficients |
DataStreams: | twpmwrlosC3.b1, twpmwrtipC3.a1 |
Description: | The statistical retrieval coefficients currently in use at the Darwin (TWP/C3) site were developed using radiosonde RS80 launched from Manus Island during the TOGA-COARE experiment. Data from Manus Island have minimal seasonality, therefore a single, annual set of coefficients was used at all three sites. Retrievals using these coefficients are sufficiently accurate especially during the local summer months (December-January). However, the Darwin site displays a summer/winter seasonality resulting in larger differences during the southern winter (May- June). Since we now have enough radiosonde soundings (RS80 and RS90) available at the Darwin site, the Darwin coefficients were modified to better reflect the local seasonality. |
Measurements: | twpmwrlosC3.b1:
twpmwrtipC3.a1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
11/13/2005 | 2314 | 03/07/2006 | 0257 |
Subject: | TWP/SKYRAD/C3 - IRT damaged |
DataStreams: | twpskyrad20sC3.a0, twpskyrad60sC3.b1 |
Description: | The analog output of the IRT was damaged by a lightning strike. The problem was corrected by replacing the instrument with a spare. The damaged IRT was returned to the vendor for repair. |
Measurements: | twpskyrad60sC3.b1:
twpskyrad20sC3.a0:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
12/20/2005 | 2330 | 01/02/2006 | 2300 |
Subject: | TWP/GNDRAD/C3 - IRT power |
DataStreams: | twpgndrad60sC3.b1 |
Description: | The IRT failed to report after a planned power outage to add lightning protection modules to the AC power wiring. The problem was corrected when a loose power connection to the logger was found, rectified, and power restored to the logger. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
12/01/2005 | 0000 | 08/24/2006 | 2359 |
Subject: | TWP/SMET/C3 - ORG data noisy due to degraded ground |
DataStreams: | twpsmet60sC3.b1 |
Description: | SMET Rain Data began to be noisy during December 2005 and the problem slowly became worse over time so that in February 2006 the ORG was reporting with a constant background value of around 0.10 mm/hr rain rate. ORG voltage showed a near constant value above the 85mV threshold. The ground for the ORG had become degraded and was lost due to corrosion. |
Measurements: | twpsmet60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
05/20/2004 | 2200 | 12/21/2005 | 2136 |
Subject: | TWP/SKYRAD/C3 - Reprocess: Longwave Calibration error |
DataStreams: | twpskyrad60sC3.b1 |
Description: | Modified pyrgeometer calibration procedures were implemented beginning in December 2003. These modified procedures introduced a calibration bias in the longwave data. The previous procedures were re-implemented at all sites between December 2005 and February 2006 to restore proper calibrations. The data collected while the incorrect procedures were in place are being reprocessing to remove the calibration bias. Note, this also affected standard deviation, maximum and minimum data fields. |
Measurements: | twpskyrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
05/20/2004 | 0100 | 12/21/2005 | 2137 |
Subject: | TWP/GNDRAD/C3 - Reprocess: Longwave Calibration error |
DataStreams: | twpgndrad60sC3.b1 |
Description: | Modified pyrgeometer calibration procedures were implemented beginning in December 2003. These modified procedures introduced a calibration bias in the longwave data. The previous procedures were re-implemented at all sites between December 2005 and February 2006 to restore proper calibrations. The data collected while the incorrect procedures were in place are being reprocessing to remove the calibration bias. Note, this also affected standard deviation, maximum and minimum data fields. |
Measurements: | twpgndrad60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
12/02/2003 | 0000 | 07/13/2006 | 2219 |
Subject: | TWP/SMET/C3 - Reprocess: Barometric Data Changed from hPa to kPa |
DataStreams: | twpsmet60sC3.b1 |
Description: | Barometric pressure data was converted from hPa to kPa in order to standardize the measurement units among ARM sites and to conform to accepted standard units determined by the scientific community. |
Measurements: | twpsmet60sC3.b1:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
03/12/2002 | 0000 | 09/26/2006 | 1435 |
Subject: | TWP/SMET/C3 - Reprocess: Tipping bucket rain gauge added |
DataStreams: | twpsmet60sC3.b1 |
Description: | A tipping bucket rain gauge was added to the SMET suite of instruments effective 20060926. Two new variables (count and rain amount) were added at the end of the twpsmet60sC1.b1 datastream. When reprocessing of this datastream occurs these variables will be added with -9999 (missing) as the value for dates prior to gauge installation. |
Measurements: | twpsmet60sC3.b1:
|